Project Description
The Utah Transit Authority (UTA), in collaboration with Salt Lake City and the Utah Department of Transportation, is extending the S-Line street car line from the current end of line at Fairmont Station (1040 East) to the heart of the Sugar House business district at Highland Drive and Simpson Ave. This project is expected to be completed in 2026.
New Elements
A new station at Highland Drive and Simpson Ave
A new double track between 500 East and 700 East
Project Goals
- Support economic development and serve the growing population of Salt Lake County
- Enhance reliable transportation to the Sugar House business district
- Bring riders closer to Sugar House Commons and the business, dining and retail district
- Provide a viable alternative to vehicular traffic
- Improve the overall connection to Sugar House
S-Line Connection
Schedule
Final design of the Extension – Fall 2024 – Spring 2025
Construction – Summer 2025 – Spring 2026
Service begins – Summer 2026
Partners
- The Utah Transit Authority (UTA)
- Salt Lake City Corporation
- The Salt Lake Redevelopment Agency
- The Utah Department of Transportation (UDOT)
Contact Us
S-Line@rideuta.com | 833-801-7433